Green Lake Fall 2012 Pond Liner Construction

September 18, 2013

Green_Lake_2012_before

Green Lake Wisconsin CRP field on a hill before pond liner construction begins in autumn 2012!

Green_Lake_excavated_pond

Green Lake WI excavated pond site.

Liner_roll_on_pallet

Synthetic pond liner on a pallet prior to unrolling for installation.

Green_Lake_liner_prep

Pond liner unrolling and preparation to be pulled across entire excavated site!

Lined_pond_fish_cribs_ballast_stone_and_trench

Lined pond with stone ballast in middle, termination trench to left and fish cribs throughout.

Green_Lake_pond_half_filled

Green Lake Wisconsin pond filling and about half way complete.  Numerous fish structure abounds!

Aerial_of_Green_Lake_pond_half_full

Aerial pic of trimmed liner, stone ballast and water filling prior to winter snowstorm Alan.

Green_Lake_winter_pic

Nearly complete!  Spring 2013 landscaping and fish stocking coming with warm weather!